HW 24: Chapter 23




23.6: Figure 23.14 shows the task durations for software project activities. Assume that a serious, unanticipated setback occurs, and instead of taking 10 days, task T5 takes 40 days. Draw up new bar charts showing how the project might be reorganized.

The setback of T5 does not significantly impact the resulting schedule of the other tasks, due to the fact that T10 is the only dependency on which rests T5 but is held back by T9 anyways.  